Yunnan's Xiaowan Hydropower Station started filling with water

Source: Xinhua Net. 18 December 2008.
http://news.xinhuanet.com/newscenter/2008-12/18/content_10525479.htm

According to Sinohydro Corporation, Yunnan Xiaowan Hydropower Station
has already closed the dam gates, and started filling with water. This
paved the way for power generation one year ahead of schedule.

Xiaowan Hydropower Station is located in the middle reaches of Lancang
River. Its installed capacity is 4200 MW, which is among the largest
dam of the eight-dam cascade in the middle and lower reaches of
Lancang River. Sinohydro Corporation is responsible for the
construction of diversion tunnel.

The construction of Xiaowan Hydropower Station started in 20th January
2002, and the river was dammed in 12th October 2004. Once it formed a
reservoir of 14.9 billion cubic meter, it can effectively regulate the
downstream flow during the flood and dry seasons, and the Lancang-
Mekong River will become a truly "golden waterway".

 
 

สมาคมแม่น้ำเพื่อชีวิต   138/1 หมู่ 4 ต.สุเทพ อ.เมือง จ.เชียงใหม่   50200
Living River Siam Association  138 Moo 4, Suthep, Muang, Chiang Mai, 50200   Thailand
Tel. & Fax.: (66)-       E-mail : admin@livingriversiam.org

ข้อมูลในเวปนี้สามารถนำไปเผยแพร่ได้โดยอ้างอิงแหล่งที่มา